Solar and NEM Requirement
Latest Infor from DUN Meeting 22 November 2023
The newly-passed amendment to the Sarawak Electricity Ordinance among others will enable homeowners to install solar panels on rooftops to produce electricity up to 50KW, said Premier Datuk Patinggi Tan Sri Abang Johari Tun Openg. He said excess electricity generated by solar panels without the requirement of a license could be sold back to the grid thus providing a source of income for house owners.
Other source: https://mut.sarawak.gov.my/web/subpage/news_view/637
Net Energy Metering
Net Energy Metering (NEM) scheme is a billing mechanism that credits direct Solar Photovoltaic (PV) system owners for the electricity they add to the grid. For example, if a residential consumer has a PV system on the rooftop, it may generate more electricity than the home uses during daylight hours. Rolling out of NEM scheme in Sarawak is to promote the use of renewable energy and the conservation of non-renewable energy at the consumer level.
NEM Contractors are responsible for carrying out necessary due diligence on the connection point to facilitate connection of generated energy. All component and equipment that are to be used and installed for the NEM scheme must comply with the latest specification approved for use in the system according to the latest version of MS1837: Installation of grid-connected photovoltaic (PV) system (refer Normative Technical Reference List).
NEM Application Documents
Forms:
PV generation interconnection application (PVGIA Form)
AC01 Form PV Meter application
Supporting Documents:
PV Panel Specification
Inverter Specification
Auxiliary Specification (Isolator, Breaker, SPD, etc.)
Solar Schematic Drawing with Interconnection Point (Certified by SEDA GCPV Designer)
Overall Layout and Location Plan
Work Schedule
Estimated Monthly Energy Generation
Copy of Chargeman L4 Certificate
Copy of SEDA GCPV Designer Certificate
Testing & Commissioning
Testing & Commissioning (T&C) shall be performed by the appointed Contractor.
T&C Report shall be submitted to Sarawak Energy Customer Service Counter for the issuance of NEM Contract, and PV Meter Fee.
Contract for Supply of Electricity (for Solar Photovoltaic Installation Under Net Energy Metering Scheme) shall be issued to and signed by the applicant prior to PV Meter Installation and system commissioning. Refer to 3.2 of MOU Guidelines.
Connection Fees and Charges
All PV metering cost shall be borne by the NEM Customer.
The unit price of smart meters for NEM are as follows:
Single phase smart meter: RM 500
Three phase smart meter: RM 1000
All other connection charges shall be borne by the NEM customer.
Solar PV Generation Capacity Limit
12 kWp for Single Phase
20 kWp for 3 Phase
Conditions:
Subject to quota availability (Not more than 75% of the total maximum transformer loading in the area from 11 hrs to 1500 hrs in the past 6 months
Applicants shall install the solar PV system with the capacity that generates energy not exceeding 75% of the average consumption for the past 12 months.
For system more than the specified capacities, the applicant shall seek approval from the Director of Electricity Supply, Sarawak.
Types of Installation Allowed
PV modules can only be installed at the following locations:
On the rooftop of building, and
On the garage, car park, and similar structures
Note: For types of installation other than mentioned, the applicant shall seek approval from the Director of Electricity Supply, Sarawak.
Connection
PV Systems shall be connected to Sarawak Energy Distribution Network in accordance with the following requirements:
Voltage: Single Phase 240V (+5% and -10%) | 3 Phase 415V (+5% -10%)
Voltage Fluctuation: The maximum voltage fluctuation range allowed due to varying solar radiation is 6%. Beyond this, the utility and consumer equipment will be at risk of overheating.
Power Factor: PV Systems shall have a leading or lagging power factor greater than 0.9 and 0.85 respectively when the output is greater than 20% of the rated output power.
LV Penetration Level for Multiple Installations
Multiple installations of PV in a same LV network will increase the current injection to the respective network. Undesirable over voltage in the LV networks might occur if the magnitude of PV current injection is greater than the load of the LV networks.
Recommendation for PV penetration limits are as follows:
Maximum allowable Solar PV capacity connected to a single LV feeder is 25 kW. This is to ensure that, under worst case scenario without load, the voltage limit of 240V (+5% and -10%) will not be violated.
Maximum allowable solar capacity connected to LV feeder pillars is 75% of the local transformer loading.
Interconnection Method
The Interconnection to Sarawak Energy Distribution Grid System shall be done through Direct Connection. Figure 1 shows the diagram of direct connection between the Prosumer’s Solar PV system and the Grid System.
The Connection shall be made in accordance with MS IEC 1857 and its updated versions.
Figure 1: The Direct Feed NEM Approach
(For reference only)
Metering Scheme
A meter shall be installed to measure the energy export of the PV system to Sarawak Energy system. This shall be achieved via a dedicated energy meter (PV Meter) installed at the output of the PV system.
PV Meter shall be installed as near as possible to Sarawak Energy Meter with maximum distance of 1 meter apart and properly labelled as “PV METER”.
PV Meter connection to the Grid System shall be done via the existing meter cut-out and neutral link. This point shall be identified as the Common Connection Point (CCP).
The customer shall be responsible for any installations after the meter.
The Contractor shall provide and install all the materials required for the system interconnection works.
All live connection and meter installation works shall be carried out by the authorised Sarawak Energy personnel only.
For looping connection between cut-outs, 16mm²/Cu or 25mm² Al cable should be used if the meter is installed in separate cabinets (with maximum distance of 1 meter).
Single phase smart meter shall be installed for application up to 12 kWp.
3-phase smart meter shall be installed for application more than 12 kWp but less than or equal to 20 kWp
Existing Sarawak Energy normal meter shall be replaced by the smart meter.
Figure 2: Connection Diagram for PV Meter and the Consumption (Sarawak Energy) Meter
Grid Connected Photovoltaic (GCPV)
Switching Coordination Operating Practices
NEM adopts Direct Feed approach
Therefore, proper isolation of customers’ PV Systems from Sarawak Energy Grid System shall be carried out to ensure safety during the Grid shutdown for repair and maintenance works. All GCPV related switching practices and caution notice standards shall comply with Sarawak Energy Distribution Operating Practices Manual,
Section 9: Grid-Connected Photovoltaic (PV) Switching Coordination Operating Practices and its prevailing versions.
Visible Caution Notices shall be affixed at the following locations:
Pillar Door
Pillar way
Dis-connector Switch – Meter Cutout fuse
NEM Contractor
All NEM applications shall be submitted by the appointed Sarawak Energy Registered Contractor (Contractor) on behalf of their client. The Contractor shall engage the following competent persons for the design, installation, and testing & commissioning of the PV system:
Internal Wiring – Certified Wiremen Grade 2, Grade 1 (EIU Licensed)
PV Designer – Certified GCPV Designer by SEDA
PV Installer – Certified GCPV Installer by SEDA, Chargeman L4 (EIU Licensed)
Meter Installations
All PV Meter installations shall be performed by Sarawak Energy Retail Department.
Link source
Disclaimer: Information publish here in this website is only for public interests only.